Employees must set up security access before they may use FABweb.
Unit assigned FABweb Unit Rep(s) must review their FABweb new acquisitions timely to review OTag records, request adjustments to OTags and OTag values as needed, and complete and submit the new acquisition record to Property Accounting in a timely manner.
State regulations require all equipment purchases be added to inventory within 90 days from procurement. This policy provides expectations for units in communicating with Property Accounting in submitting equipment records throughout the year and at each year-end to ensure all equipment purchased in the current fiscal year are completed timely and on inventory by the end of each fiscal year. OTag records are not always able to be created in the correct desired dollar amount and quantity, which requires unit scrutiny of OTag records and values for adjustments prior to completion and submission to Property Accounting.
All Units must strive to meet these equipment processing goals for inventoried equipment in order to remain in compliance with State of Illinois regulations.
Units should review each new acquisition in FABweb and request changes to OTags and values within 30 days from the OTag creation date:
Units must strive to submit a new acquisition in FABweb within 30 days from the OTag creation date or adjustment date. Unit Reps will receive an email each week if there are any outstanding OTags to be submitted within their FABweb new acquisitions inbox. These records must be submitted timely as follows:
If an enhancement or upgrade is being made to existing equipment, treat it as a new acquisition. Indicate the parent-child relationship when processing the new acquisition in FABweb.
Units not submitting FABweb records timely, will be subject to the following procedure throughout the year with more stringent timing required at year end:
Units may purchase and/or receive items very late in the fiscal year, making timely record completion difficult. Equipment records must be completed in the same fiscal year in which they were purchased. As a result, units must submit all current fiscal year records by the end of University Accounting period 12. This due date for FABweb new acquisition at year-end is further outlined in the annual year-end closing procedures. UPAR helps track these required submissions and units can reach out to their assigned staffer in UPAR new acquisitions group for more guidance and direction at year end.
First Published
June 2011
Last Updated
March 2025
Last Reviewed
March 2025